First Smart Hospital in Canada
Challenges
- Newly constructed acute-care hospital for which Johnson Controls has a 30-year service agreement. In first year of operation; there is currently a high volume of work requests
- Performance-based agreement requires meeting defined targets such as temperature, humidity and negative pressure in critical spaces
- Requires a unified energy management solution
Solutions
- Johnson Controls OpenBlue technologies continuously and proactively identified HVAC issues
- Provided alerts to compliance variance and optimal performance of systems
- Automated monthly energy reporting and identified energy faults in near real-time
Results
- Reduction in preventive maintenance efforts of 600 hours per year for estimated avoided maintenance costs of $60,000 per year
- Asset Manager in first year of operation already mitigated 4,000 hours of non-compliance not captured in the BAS
- Automated reporting has reduced manual effort by 16 hours per month for an estimated annual savings of $20,000 per year
Related Items
OpenBlue
Applying data from both inside buildings and beyond, our customers can now manage operations systemically.
Net Zero Buildings
Achieve decarbonization and renewable energy targets and optimize building performance.